The US Coast Guard (USCG) approved the Fall 2024-Spring 2025 schedule for full and half channel closures necessary for installation of the new bridge spans. Upcoming dates are as follows:
START DATE | END DATE | |
FULL CLOSURE – No bridge openings – No marine traffic | September 16, 2024, 6:00 A.M. | September 20, 2024, 6:00 P.M. |
PARTIAL CLOSURE East half open 37.5’ channel width, west half closed | September 23, 2024 | October 25, 2024 |
The channel under the bridge will be open at full width (75 feet) only on the weekends listed below:
Saturday, September 21 – Sunday, September 22, 2024
Saturday, October 26 – Sunday, October 27
Please see the Updated Public Notice for all full and half closure dates.
Dates are subject to change based on weather conditions and production factors.
Any schedule changes or impacts to river and roadway traffic will continue to be posted to the Travel Advisory page of this website.
To access the USCG’s Local Notice to Mariners, go to Useful Links.
If you have questions or comments, please Contact Us.
The Project Team appreciates your continued support and understanding during the construction phase of this important bridge replacement.